5-Day Work Plan
Day 1: Demolition and Preparation

Removal of old tiles, sanitary ware, furniture, and other elements.

Disconnection of utilities (water, electricity).

Debris removal and surface cleaning (walls and floors).

Initial plumbing and electrical layout, if required.

Day 2: Rough-In Work

Wall and floor leveling (plastering, screeding).

Installation of waterproofing on the floor and in high-moisture zones.

Continuation of pipe and wiring layout.

Surface preparation for tile installation.

Day 3: Tiling Begins

Marking and beginning of wall tile installation.

Tiling in the bathtub/shower area.

Use of level and spacers for precise alignment.

Grouting of completed sections (if dry by end of day).

Day 4: Tiling Completion and Plumbing Installation

Completion of wall and floor tiling.

Grouting all remaining tiled areas.

Installation of the bathtub or shower cabin.

Mounting of concealed plumbing components (flush systems, mixers, water inlets).

Day 5: Finishing and Handover

Installation of the sink, mirror, and furniture.

Connection and testing of plumbing for leaks.

Installation of sockets, lighting fixtures, and ventilation.

Final cleaning of the space.

Handover to the client and signing of the work completion report.